Electrical Wiring of the School…

The Prince and Princess Academy Project Team hired electricians to do the wiring of the School. Thanks to all those who supported us, we have paid the Masons fixing the doors and windows. The next phase of the project is the ceiling works and installation of electrical sockets, lamps and fans. We hope you will continue to support the project. Thank you. 

Installation of Metal Doors and Windows of the Classrooms in Progress

The Prince & Princess Academy Project Team has begun the installation of the metal doors and windows. We were able to buy the cement bags but we had an agreement with the masons to pay them later which they accepted. Hopefully we will be able to raise some more funds to pay them. We are grateful to all those supporting the dream of the team to proving education to children in our community, Thank you! ❤
We will keep you updated.

The Prince and Princess Academy Project Team has received the full estimate for the installation of the metal doors and windows of classrooms provided by the Mason.

Materials needed. *15 bags of Cement(50kg) =$10 × 15 bags = $150.

*Cost of paying Masons= $205. *Total Cost = $335.

We hope you will continue to support the project to fulfill the dream of providing quality education for children in our community so they can grow up to become productive and responsible citizens to help build their communities as well. We are most grateful to all those who supported the making of the metal doors and windows. It will be exciting to see the doors and windows fixed.