The Prince & Princess Academy Project Team is currently working on the front fencing. We are also raising funds to build the school office. Below is the estimate for the construction of the office structure.

Estimate:
Cement bags= $10 × 50 bags = $500
Iron rods = $12 × 10 (11.5mm) = $120
Wood (2×6) = $6 × 80= $480
Aggregate sand = $127 × 2 trips = $254
Cost of labour (Mason) = $300
Total: $1,654.

The academic year for nursery, kindergarten, and primary suspended due to covid-19 and will resume in January 2021, we hope the school will be open in January too.